Week One (Dec 18-22):
- general meeting with staff
- meeting with Jen & Mike
Week Two (Dec 25-29)
- prepare material for #1 meeting (LOGIN/LOGOUT, front page copy, prioritize tools)
Week Three (Jan 1-5)
- send out material for meeting #1
Week Four (Jan 8-12)
edit, week four merged with week five
- #1 meeting
- prepare material for #2 meeting
- begin wireframes
- Kate to NIGERIA
Week Five (Jan 15-19)
- resolve any malingering issues from #1 meeting
- send out material for #2 meeting (NAVIGATION)
- wireframes
Week Six (Jan 22-26)
- #2 meeting
- send materials to Jen/board meeting
Week Seven (Jan 29-Feb 2)
- prepare material for #3 meeting (DESIGN)
- wireframe prototypes
- Kate returns to TORONTO
Week Eight (Feb 5-9)
- #3 meeting, addressing final issues -> DESIGNERS AND CODERS MUST BE PRESENT
Week Nine (Feb 12-16)
- line up design/usability peers
Week Ten (Feb 19-23)
- finalized wireframes for critiquing
Week Eleven (Feb 26- Mar 2)
- wireframe peer critique
Week Twelve (Mar 5-9)
- FINAL MEETING (wireframe presentation)
- design tweaking
Week Thirteen (Mar 12-14)
- design tweaking
- if time, create plans to implement design